To avoid rush charges and possible shutdown delays:
it is important to check inventory and pre-order often overlooked items for the Recausticizing/Lime Kiln Plant
White Liquor & Mud Washing Pressure Filters:
- Pressure Filter Support Tubes – Lead time: 10-12 weeks.
- GORE ® Filter Socks – Lead time: 4 to 6 weeks.
- Polypropylene Filter Socks – Lead time: 4 to 6 weeks.
- Pressure Filter Fasteners, Bolts, Studs, Nuts and Washers – Lead time: 2 to 4 weeks.
- Never-Seez and Lock Tite (red).
- Mechanical drive shaft seal.
- Torque Stix, torque wrench and other appropriate tools.
- Dome “O”-Ring seal (if required) – In stock Vancouver, BC Warehouse.
Lime Mud & Dregs Pre-Coat Filters:
- Filter Cloth – Lead time: 4 weeks.
- Drainage Grids, Full Set for Complete Replacement – Lead time: 4 to 6 weeks.
- Pre-Coat Doctor Blades – Lead time: 8 to 10 weeks.
- Wear Plate for Vacuum Valve – Lead time: 6 weeks depending if drawing is on file.
- Caulking Cord – Lead time: 1 to 2 weeks depending on supply.
- Pneumatic Hammer & Wheels for Installation – Lead time: 1 to 2 weeks.
- Hot Knife for Cloth Trimming and Touch up – Lead time: 1 to 2 weeks.
- Division Strips – Lead time: 8 to 10 weeks.
- Drum & Agitator Bearings and Housings – Lead time: 7 to 10 weeks.
Slaker, Causticizers & Other Agitators:
- Slaker Grits Screw Bushings – Lead time: 3 to 4 weeks.
- Agitator Hub & Blades – Lead time: 10 to 12 weeks.
- Agitator, Bolts & Fasteners – Lead time: 2 to 4 weeks.
- Spare Parts for Clarifier Drives – Lead time: 8 to 10 weeks.
Lime Kiln:
- Stop Blocks – Lead time: 4 to 5 weeks
- Bucket Elevator Pins – Lead time: 2 to 3 weeks
- Seal Replacement Leaves (if required) – Lead time: 4 to 6 weeks
- Bull Gear Pins – Lead time: 6 to 8 weeks